Fuse box out and a full rewire in a small 1920s house
Example project

- Home
- 1920s one-story house in Auburn with a full basement, about 1,100 sq ft
- Original request
- Replace the fuse box and the knob-and-tube still in use in every room
- Found
- Eight screw-in fuses, two of them larger than their wire can safely carry, feeding knob-and-tube throughout
- Work
- New 200-amp panel, meter base and service wires; every circuit rewired with grounded cable
- Access
- Open attic above and a full basement below, so only a few small openings in the plaster
- Timeline
- About eight working days, with the utility shutoff on day one and the inspection before closing up
- Cost
- $24,500
Scope of work
The fuse box and old service taken out, a 200-amp breaker panel, meter base and service wires fitted, and every room rewired with grounded cable, new boxes, outlets and switches, plus new circuits for the kitchen counter, bathroom and laundry. Old wires are disconnected and left in the closed walls, and the runs in the attic and basement are pulled out. Permit and inspection are included; plaster patching is not.
Project overview
In this example, a 1920s house in Auburn still runs on its fuse box, and the knob-and-tube behind it reaches every room. Two of the eight fuses are larger than the wire behind them can safely carry.
In a small house with an open attic and a full basement, the panel and the rewire make sense as one job. New cable is fished down from the attic and up from the basement, so only a handful of small openings are cut in the plaster, and the new panel has room for the kitchen, bathroom and laundry circuits the house never had. The house is inside Auburn city limits, so the permit and inspection come from L&I.
The goal
The goal is a house with a new panel, no live knob-and-tube left and grounded circuits where modern appliances plug in, with the permit and circuit list on file.
Process
- Before work Every circuit traced from the fuse box, the permit bought and the utility shutoff booked.
- Day one Power off, the old service and fuse box out, the new meter base and panel in, power back once the utility reconnects.
- Days two to six Rooms rewired from the attic and basement, a few at a time, with power back on each evening.
- Day seven Inspection while the new cable and openings are still visible.
- Day eight Devices and covers fitted, old runs in the attic and basement pulled out, and a circuit list handed over.
Planning right
- Never swap a blown fuse for a bigger one. A fuse that blows is doing its job.
- Keeping a few knob-and-tube circuits is sometimes possible, but in a house this size most owners replace them all at once.
- Ask for the circuit list at the end. It shows an insurer or a buyer exactly what changed.
- Book the plasterer for after the inspection. The openings stay open until the inspector has seen the cable.