Example Knob and Tube Projects in Auburn, Washington

Each example follows one older-house wiring job from what turns up behind the walls to the finished work. Each one lists the house, the old wiring, the work, how long it takes and roughly what it costs. Only a small share of Auburn’s homes were built before 1950, so the examples come from the city’s older houses and from Puyallup and Enumclaw, where a larger share of homes are that old.

Fuse box out and a full rewire in a small 1920s house

Example project

New gray breaker panel on a painted basement wall below the floor joists, beside a small basement window
Home
1920s one-story house in Auburn with a full basement, about 1,100 sq ft
Original request
Replace the fuse box and the knob-and-tube still in use in every room
Found
Eight screw-in fuses, two of them larger than their wire can safely carry, feeding knob-and-tube throughout
Work
New 200-amp panel, meter base and service wires; every circuit rewired with grounded cable
Access
Open attic above and a full basement below, so only a few small openings in the plaster
Timeline
About eight working days, with the utility shutoff on day one and the inspection before closing up
Cost
$24,500

Scope of work

The fuse box and old service taken out, a 200-amp breaker panel, meter base and service wires fitted, and every room rewired with grounded cable, new boxes, outlets and switches, plus new circuits for the kitchen counter, bathroom and laundry. Old wires are disconnected and left in the closed walls, and the runs in the attic and basement are pulled out. Permit and inspection are included; plaster patching is not.

Project overview

In this example, a 1920s house in Auburn still runs on its fuse box, and the knob-and-tube behind it reaches every room. Two of the eight fuses are larger than the wire behind them can safely carry.

In a small house with an open attic and a full basement, the panel and the rewire make sense as one job. New cable is fished down from the attic and up from the basement, so only a handful of small openings are cut in the plaster, and the new panel has room for the kitchen, bathroom and laundry circuits the house never had. The house is inside Auburn city limits, so the permit and inspection come from L&I.

The goal

The goal is a house with a new panel, no live knob-and-tube left and grounded circuits where modern appliances plug in, with the permit and circuit list on file.

Process

  1. Before work Every circuit traced from the fuse box, the permit bought and the utility shutoff booked.
  2. Day one Power off, the old service and fuse box out, the new meter base and panel in, power back once the utility reconnects.
  3. Days two to six Rooms rewired from the attic and basement, a few at a time, with power back on each evening.
  4. Day seven Inspection while the new cable and openings are still visible.
  5. Day eight Devices and covers fitted, old runs in the attic and basement pulled out, and a circuit list handed over.

Planning right

  • Never swap a blown fuse for a bigger one. A fuse that blows is doing its job.
  • Keeping a few knob-and-tube circuits is sometimes possible, but in a house this size most owners replace them all at once.
  • Ask for the circuit list at the end. It shows an insurer or a buyer exactly what changed.
  • Book the plasterer for after the inspection. The openings stay open until the inspector has seen the cable.

Get a free quoteMore about fuse box replacement

An old fuse box and a later breaker panel combined into one

Example project

Old screw-in fuse box in a basement next to a newer breaker panel, with a bare bulb above
Home
1930s house in Puyallup with a basement
Original request
Retire the old fuse box that still sits beside the breaker panel
Found
The fuse box feeds four original knob-and-tube circuits upstairs; the breaker panel feeds later circuits
Work
Both replaced by one new breaker panel at the same service size, each old circuit on a breaker sized to its wire
Timeline
One working day with the power off, then the inspection
Cost
$5,400

Scope of work

The fuse box and the older breaker panel both taken out, one new breaker panel fitted at the same service size, the circuits from both landed on breakers sized to their wire, every circuit labeled, and the permit and inspection. Rewiring the four knob-and-tube circuits is a later phase and not in this price.

Project overview

In this example, a 1930s Puyallup house has a breaker panel that was added decades ago, but the old fuse box beside it was never taken out. It still feeds four knob-and-tube circuits upstairs, so the house has two sets of protection and nobody is sure which switch turns off what.

Combining them into one new panel puts every circuit in one place with a label. The four old circuits go on breakers sized to their wire, and the panel keeps spare spaces for when those rooms are rewired. The address is inside Puyallup city limits, so the permit comes from L&I.

The goal

The goal is one panel with every circuit labeled and properly protected, and spare spaces ready for the rewire that comes next.

Process

  1. Before work Each circuit traced to its room, and the address checked for the right permit office.
  2. Work day Power off, both boxes out, the new panel in, every circuit landed and labeled, power back on.
  3. Inspection The inspector checks the panel and the breaker sizes.
  4. Next phase The four knob-and-tube circuits are rewired room by room when the owners are ready.

Planning right

  • Knob-and-tube on a breaker is still knob-and-tube. The new panel makes it safer to keep for now, not new.
  • Some Puyallup mailing addresses are outside the city and come under a different permit office. The street address decides.
  • A labeled panel saves time on every later job in an older house.
  • Insulation can go around the remaining knob-and-tube only after an electrician surveys it under Washington’s rule.

Get a free quoteMore about fuse box replacement

Upstairs bedrooms rewired from the attic

Example project

Old attic timbers with knob-and-tube wiring on white porcelain knobs, lit by a single bulb
Home
Early-1900s house in Enumclaw, one and a half stories
Original request
Replace the knob-and-tube that still feeds the two upstairs bedrooms and the hall
Found
Two live knob-and-tube circuits running along the attic timbers; the main floor was rewired years ago
Work
New grounded cable fished down from the attic to every outlet, switch and ceiling light upstairs
Timeline
Four working days, then the inspection, then patching and attic insulation
Cost
$8,400

Scope of work

Both old circuits traced and disconnected, new grounded cable run from the panel and fished down from the attic to every outlet, switch and ceiling light in the two bedrooms and the hall, new boxes and devices, the old runs on the attic timbers taken down, and the permit and inspection. Plaster patching and attic insulation are not included.

Project overview

In this example, the main floor of an early-1900s Enumclaw house was rewired years ago, but the two upstairs bedrooms and the hall still run on knob-and-tube strung along the attic timbers. The owners want to insulate the attic, and they would rather replace the old wiring than have it surveyed and left in place.

With the attic open above, most new cable drops straight into the walls below, so only a few small openings are needed where a wire meets a blocked stud bay. The family keeps using the main floor throughout. Once the inspector has seen the new cable, the old runs come down and the attic is ready for insulation.

The goal

The goal is an upper floor on grounded circuits, no live knob-and-tube left in the house, and an attic ready for insulation.

Process

  1. Before work Circuits traced from the panel, the permit bought, and boards laid across the attic joists to work from.
  2. Days one to three New cable run from the panel and fished down from the attic, one room at a time.
  3. Day four New devices and lights connected, and the old circuits disconnected at the panel.
  4. Inspection The inspector checks the new cable in the attic and at the openings.
  5. Afterwards Old runs taken down from the timbers, then patching and attic insulation by others.

Planning right

  • Washington lets insulation go around knob-and-tube only after an electrician surveys it and certifies it in writing. Replacing it first takes those circuits out of that rule.
  • Note the new cable routes before the insulation goes in. Later work is easier when they are known.
  • A phase like this follows circuits, not rooms. Here the two old circuits happen to cover the whole upper floor.
  • Ask whether old runs will be pulled out or only disconnected. Here the attic runs come out because they can be reached.

Get a free quoteMore about room-by-room rewiring

A whole-house rewire in four phases

Example project

Empty upstairs room in an older house with plaster walls, a ceiling attic hatch and folded drop cloths
Home
1920s house in Auburn, one and a half stories, about 1,600 sq ft, plaster walls
Original request
Rewire the whole house without moving out
Phases
Kitchen, bathroom and laundry first, then the main-floor rooms, then upstairs, then the basement
Work
Every knob-and-tube circuit replaced with grounded cable, with a permit and inspection for each phase
Timeline
Four phases of about a week each, spread over two months
Cost
$27,500

Scope of work

Each phase traced and mapped, new grounded cable, boxes, outlets, switches and light connections for the circuits in that phase, the old circuits disconnected, an inspection before any opening is closed, and an updated circuit map at the end of each phase. The panel was replaced in an earlier job, and plaster patching is priced separately.

Project overview

In this example, a family with two young children lives in a 1920s Auburn house that still has knob-and-tube on most circuits. The breaker panel was replaced a few years ago, so the wiring is what remains, and moving out for it is not an option.

The rewire is split into four phases that follow the circuits. Kitchen, bathroom and laundry go first because that is where the heavy loads are. Each phase is inspected before its openings are closed, and the family gets an updated circuit map after each one, so everyone knows which circuits are new.

The goal

The goal is a house with every knob-and-tube circuit replaced or disconnected by the end of phase four, without the family ever moving out.

Process

  1. Phase one Kitchen counter, bathroom and laundry on new grounded circuits.
  2. Phase two Living room, dining room and the main-floor bedroom.
  3. Phase three Upstairs rooms, fished down from the attic hatch.
  4. Phase four Basement lights and outlets, then the last old circuit disconnected.
  5. After each phase Inspection, an updated circuit map, then patching.

Planning right

  • Phases are drawn around circuits. One old run can feed two bedrooms and a hall light.
  • Whether the job runs under one permit or several is settled with L&I before phase one.
  • Plan which rooms will be out of use each week, and keep one bathroom working throughout.
  • Expect some plaster dust from each opening, even with covers down.

Get a free quoteMore about room-by-room rewiring